Posted on May 26, 2026 at 7:23 AM by John Guccione
ACTIVE LOCATION SUMMARY:
Berkeley Ct (Stratford to Linden Loop):
Aggregate base course fine grading is scheduled for this week in preparation for asphalt base course paving, which is currently planned for Friday, weather permitting. An additional notice will be distributed to residents with full details regarding the upcoming paving operations. Please be advised that fine grading activities may cause delays for motorists, as access to portions of the roadway will be temporarily limited during construction operations.
Broadmoor Pl (Hazel to Greenwood) & Somerset Ave (Cherry to Broadmoor):
Phase 1 of concrete ribbon curb installation is scheduled for today along the west side of Broadmoor Place and the south side of Somerset Avenue. This work will limit driveway access for some residents. Impacted residents were notified last Friday. Phase 2 of curb installation is anticipated to occur next week on the opposite sides of the roadways.
Oakley Ave (Hazel to Greenwood):
Underground utility work is currently underway and is expected to be completed this week. Concrete sidewalk repairs are scheduled to begin next week.