2025 Hazel Avenue Reconstruction Project

Subscribe to receive updates on the 2025 Hazel Avenue Reconstruction Project.

View All Posts

Nov 07

Hazel Project Update – 11/07/2025

Posted on November 7, 2025 at 7:06 AM by Cory Siegel

This week, the contractor’s underground crew advanced the new storm sewer installation in the unpaved roadway segment between Chestnut Street and Wayne Avenue. This marks the final phase of all underground work and is planned to continue into next week.

Simultaneously, pavement excavation began in the remaining work zone to prepare for subbase improvements and the installation of concrete curb, sidewalk, and driveway elements. These surface improvement tasks are scheduled to start early next week once excavation progresses further down the road.

We appreciate your continued patience and support as we improve Deerfield’s infrastructure. If you have any questions, please contact the Village of Deerfield Engineering Department at 847-317-2490 and ask about the Hazel Avenue Infrastructure Project.