Sep 29

Waukegan Rd Project Update - 9/29/2023

Posted on September 29, 2023 at 1:47 PM by Justin Keenan

This week (Sept 25 – 29), the contractor continued with concrete and asphalt restoration work in the outside lanes and on Warwick Road, though production wasn’t ideal due to the weather impacts earlier in the week. The contractor will continue this work over the weekend and into next week. Next week’s work will also include the pavement restoration at North Avenue and the Village has been in coordination with the North Trails HOA about this work. Once these items are completed, the contractor will restripe the road and will be ready to open the road back up to four lanes. Any remaining items that would need to be completed would be done so under daytime lane closures between 9am – 3pm. 

The Village appreciates your cooperation during this important improvement. For more information, please contact the engineering department at 847.317.2490.

Sep 22

Waukegan Rd Project Update - 9/22/2023

Posted on September 22, 2023 at 2:54 PM by Tyler Dickinson

This week (Sept 18 – Sept 23), the contractor began pouring the concrete curbs and sidewalks in the outside lanes. This concrete work includes the curbs along Warwick Road which is still under a one lane traffic configuration in the eastbound direction. Next week and weather depending, the contractor will complete any remaining concrete work, potentially complete the pavement repairs along Waukegan Road, complete the parkway restoration, and place at least the first layer of pavement on Warwick Road. Weather depending, the project is anticipated to be substantially completed with traffic opened back up to normal operations in the next two weeks. Any remaining items that would need to be completed would be done so under daytime lane closures between 9 a.m. – 3 p.m. 

The Village appreciates your cooperation during this important improvement. For more information, please contact the engineering department at 847.317.2490.

Sep 15

Waukegan Rd Project Update - 9/15/2023

Posted on September 15, 2023 at 3:43 PM by Tyler Dickinson

This week (Sept 11 – Sept 15), the contractor completed the pavement patching within the center lanes of Waukegan Road and began the curb and sidewalk repairs in the outside lanes. The contractor will continue working in the outside lanes over the next few weeks to complete the project. Also this week, the contractor began pavement repairs on Warwick Road from Waukegan Road to Warwick Court. This work will require Warwick Road to be reduced to one lane beginning Monday to allow the contractor enough room to safely complete the repairs. During this time, east bound traffic will be permitted and west bound traffic will be required to use an alternate route to reach Waukegan Road. District 109, LRS and the impacted residents will all be notified prior to the implementation of one-way traffic. See below map. 

Warwick One Way

The Village appreciates your cooperation during this important improvement. For more information, please contact the engineering department at 847.317.2490.