2018 Street Rehab Project

2018 Capital Improvement Program Storymap

Jul 11

[ARCHIVED] Hazel Project Update - 7/11/2025

The original item was published from July 11, 2025 2:54 PM to July 11, 2025 2:56 PM

Construction Update – 7/11/2025

This week on the east end, the contractor continued prepping the roadway for upcoming concrete work, which is expected to start next week with the installation of sidewalk and curbs and gutters. The contractor anticipates paving this section of roadway the week of the 21st.  Also this week, the underground contractor worked on installing water services between the bridge and Prairie Avenue which will carry into next week. 

Residents impacted by either water or concrete related disruptions continue to be notified in advance through hand delivered notices.

We appreciate your continued patience and support as we improve Deerfield’s infrastructure. If you have any questions, please contact the Village of Deerfield Engineering Department at 847-317-2490 and ask about the Hazel Avenue Infrastructure Project.