Waukegan Road Water Main Replacement
This week, the contractor continued to transfer water services over to the new main north of Orchard Street during the day and in the downtown area at night. With Deerfield High School on summer break, the contractor installed the traffic control from Greenwood Avenue to North Avenue early this week and began prep work. It is anticipated that all water main items will be completed in the south section by next Tuesday.
Next week, the contractor will complete the final water main connections at Elder Lane on Monday and Hazel Avenue on Tuesday. Both connections will require daytime closures of the intersections. Over the next two weeks, the contractor will work to complete all restoration items south of Greenwood Avenue, including the downtown area. Water main work north of Greenwood Avenue will being early next week and is anticipated to be completed by mid-September.
The Village appreciates your cooperation during this important improvement. For more information, please contact the engineering department at 847.317.2490.