6 a.m. Paving Tomorrow Montgomery, then 9 a.m. Paving on Kipling (August 10th Paving Schedule)

Posted on August 9, 2022 at 5:43 PM by John Guccione

The Village has approved a 5:30 a.m. start time for tomorrow (August 10th) at Montgomery, so that paving operations may begin promptly at 6 a.m. 

Paving Schedule for Wednesday, August 10, 2022:

  • 5:30 a.m. Start Time @ Montgomery 
  • 6:00 a.m. Mix Arrives Paving Begins @ Montgomery
  • 9:00 a.m. Approximate Completion of Montgomery
  • 9:30 a.m.  Approximate Paving to Begin on Kipling, Hermitage & Longfellow. (Contractor may return to complete Whittier depending upon production)

The early start is required so that the contractor may complete final surface paving on Montgomery and other locations within the village. This early start is required due to contractor availability, and the Village’s need to complete paving and pavement marking before school starts next week. 

 Once placement is completed and this layer of asphalt has had time to cool, traffic will be permitted to travel across it (approximately 1 hour after placement).   If you must travel upon freshly placed asphalt, please do not turn the wheel of your vehicle while standing still. This will damage the fresh asphalt.   Turning the wheel may only be done when your vehicle is in motion.