Saturday Paving Canceled Due to Rain

Posted on July 23, 2022 at 6:47 AM by John Guccione

Saturday's paving operation is canceled due to rain.

On Monday, July 25th the contractor will pick up where they left off on Friday to complete the 5 inch base paving on Price Lane, beginning at 7am.

After completing asphalt base paving on Price Lane, the contractor will move to Montgomery Road to perform 1 inch leveling paving (around 10 or 11am).  They should complete the "leveling" paving on Montgomery around 1pm on Monday and will then move over to begin 1 inch leveling paving on Kipling Place. 

Paving for Longfellow, Hermitage, Whittier and Byron is now moved to Tuesday, July 26. 2022.

Paving operations will include heavy truck traffic and will present major delays to through traffic. During this time and if possible, please avoid the construction operations and utilize adjacent roadways. All driveways will be accessible at the completion of each work day. ALL OPERATIONS DEPENDENT UPON WEATHER:  Any cancelations will be communicated via the project blog.