Paving Continues Saturday (July 23rd) on Price, Montgomery & Kipling

Posted on July 22, 2022 at 4:04 PM by John Guccione

On Saturday, July 23, 2022 the contractor will pick up where they left off today, and complete the 5" base paving on Price Lane, beginning at 7am.

After completing asphalt base paving on Price Lane, the contractor will move to Montgomery Road to perform 1 inch leveling paving (around 10 or 11am).  They should complete the "leveling" paving on Montgomery around 1pm and will then move over to begin 1 inch leveling paving on Kipling Place. They intend to complete their day of paving on Saturday at Kipling Place.

Paving for Longfellow, Hermitage, Whittier and Byron is now moved to Monday, July 25. 2022.

Paving operations will include heavy truck traffic and will present major delays to through traffic. During this time and if possible, please avoid the construction operations and utilize adjacent roadways. All driveways will be accessible at the completion of each work day. ALL OPERATIONS DEPENDENT UPON WEATHER:  Any cancelations will be communicated via the project blog.