Construction Update for Week of June 13, 2022

Posted on June 13, 2022 at 7:18 AM by John Guccione

Charing Cross:  Pavement base paving was completed last week.  Adjustments to underground structures will take place this week. Restoration of parkway will occur in the next 1-2 weeks. The final lift of asphalt will be placed in 2-4 weeks.

Gordon Terrace & Plum Tree:   Pavement base paving was completed last week.  Adjustments to underground structures will take place this week. Restoration of parkway will occur in the next 1-2 weeks. The final lift of asphalt will be placed in 2-4 weeks.

Longfellow, Hermitage, Byron, Whittier and Kipling:   Curb placement will begin Monday, June 13 after 11am.

Montgomery Rd:  Curb placement will begin Monday, June 13 at 7:30 am.  Sidewalk placement will follow. 

Rosewood Ave:    Underground operations will begin on Tuesday, June 14. Underground work will include water main installation and minor repairs to storm sewer laterals relating to roadway drainage. 

Price Lane:    One final phase of underground will be completed on Monday and Tuesday.  Pavement removal will take place towards the middle of this week.  Additional notification will be provided prior to this operation.