Construction Update for Week of June 6, 2022

Posted on June 6, 2022 at 7:23 AM by John Guccione

Charing Cross:  Pavement removal will be completed on Monday, June 6.  Grading of subbase will continue in preparation for paving, which is planned for Wednesday, June 8.

Gordon Terrace & Plum Tree:   Grading of subbase will continue in preparation for paving, which is planned for Wednesday and Thursday, June 8 and June 9. 

Longfellow, Hermitage, Byron, Whittier and Kipling:   Underground work begins Monday, June 6 and will continue through the week.

Montgomery Rd:  Removal of curb and sidewalk along the north side begins Monday, June 8.  Placement of new curb is planned Wednesday, June 8. Impacted residents were notified last Friday of this upcoming operation.

Price Lane:    Underground operations were completed last week on Price Lane. Pavement removal will take place towards the middle of this week.  Additional notification will be provided prior to this operation.