Construction Update for Week of May 9, 2022

Posted on May 8, 2022 at 1:45 PM by John Guccione

This email contains a forecast of construction operations for the upcoming week. Please note that this schedule is subject to change, pending weather conditions and contractor availability.

Plum Tree & Gordon:  Installation of the storm sewer mainline will continue on Plum Tree and Gordon this week.

Charring Cross: Replacement of a small section of water main at Pine and Charring Cross will take place on Monday, May 9th which will result in water main shutdown and disruption of water service on Monday from 10am to 3pm. Resident who will be impacted were notified on Friday using "Village of Deerfield door hangers". Underground work on Charring Cross will be completed on Tuesday. 

Price Lane:  Water main installation will begin on Tuesday or Wednesday of this week. 

Locations Awaiting Completion of the School Year

  • Montgomery
  • Rosewood
  • Kenmore
  • Longfellow
  • Hermitage
  • Byron
  • Whittier