View All Posts

Jun 11

Construction Update for Week of June 14

Posted on June 11, 2021 at 3:51 PM by Tyler Dickinson

Ambleside, Dimmeydale, and Windcrest

This week, the contractor was able to complete the first round of the curb installation as well as approximately half of the sidewalk. Today, the contractor installed the sidewalk in front of all impacted driveways, thereby allowing access again on Monday once the contractor opens them up.

Next week, the contractor will complete the remaining sidewalk and also begin curb and sidewalk removals on the other side of the streets. These removals will impact driveways beginning on Wednesday. A hand delivered notice with more information was distributed this afternoon.


Greenwood Avenue


Greenwood Avenue will be open for parking this weekend and residents are encouraged to park as usual. There will not be a need to park along Deere Park Ct until Monday morning.

The contractor continued the water main and storm sewer installation this week, including the new water main connection out to Deere Park Ct. With the exception of the private water service transfers to the new main, the contractor anticipates completing the remaining underground work by the end of the week. Once appropriate testing is completed on the water main, the contractor will return to complete the water service transfers to the new main.


Reminder that trash collection at all locations has been rescheduled for early pickup, starting at 6:30am. This is in an effort to avoid any conflicts with the construction crews.