View All Posts

May 27

Woodvale Ave Update - 5/26/2020

Posted on May 27, 2020 at 10:42 AM by John Guccione

WORK COMPLETED
Last Friday, the contractor completed excavation and sub-base preparation along the north/east side of the roadway and began removal of Woodridge Court.

ANTICIPATED WORK THIS WEEK
This week the contractor will complete pavement removal and sub-base preparation on Woodridge Court.

On Thursday and Friday of this week, the contractor will pour the curb and gutter along the north/east side of the roadway, along with any remaining sidewalk and concrete driveway approaches.

LOOK FORWARD 
Next week the contractor will "fine grade" the stone area in preparation of paving of the northeastern portion of the roadway which is planned for next Friday (weather permitting).

CONSTRUCTION RELATED IMPACTS
Impacts to residential driveways will be minimal during this phase of concrete placement. Residents who will experience access impacts have been notified. 

This phase of construction will result in heavy truck traffic as material is moved in and out of the site.  The northbound detour will remain in place. However, delays may be experienced within the project limits during daytime operations.  In most cases, the contractor is able to allow passage in short order.  We appreciate your continued patience and understand as we work to complete this project.

TRASH: During the roadway reconstruction phase, please continue to move trash out close to the curb as you normally would. The contractor will be in early on Tuesday mornings to move the trash from the parkway to the street, thereby allowing the trash collection trucks to empty them.

CORONAVIRUS
The Village’s infrastructure construction projects fit under an exemption per the Governor’s Stay at Home order. Outdoor activities, like construction projects, generally will provide for good social distancing that poses little risk of transmission, but it is still important to ensure the ability to wash or sanitize hands and take other precautions. Village and contractor personnel will continue to practice safe social distancing and sanitation efforts during the construction.

If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak to with someone regarding the Woodvale Avenue Project.