Traffic Cone

2018 Street Rehab Project

The original category was published from April 19, 2018 3:24 PM to April 19, 2018 3:25 PM

Aug 16

[ARCHIVED] Construction Update for week of August 16

The original item was published from August 16, 2021 2:49 PM to August 16, 2021 2:51 PM

Ambleside, Dimmeydale, and Windcrest
Directional boring for street light conduit began today and weather depending, is expected to be completed by the end of the week. Next week, the contractor will be paving the final surface course. Additional notification will be distributed once the final paving schedule has been determined.
 
Greenwood Avenue
With the completion of the final surface paving last Friday, this location has been substantially completed. The remaining parkway restoration and site cleanup will be completed as weather allows. 
 
Elder Lane
Last week, the contractor completed the curb installation on the north side of the road. Today, the contractor is working to install the curb on the south side of the road as well as the remaining driveway apron and sidewalk locations. Later this week, the contractor will begin pavement removals. Additional notifications will be distributed prior to the start of this work. 
 


Jul 27

[ARCHIVED] Construction Update: Week of July 26

The original item was published from July 27, 2021 7:32 AM to July 27, 2021 3:30 PM

Ambleside, Dimmeydale, and Windcrest
Directional boring for street light conduit is planned to begin in the next couple weeks, pending contractor availability. The final roadway surface placement will be coordinated with other locations and the completion of the street light work in around 2-3 weeks.   
 
Greenwood Avenue
Detector loops for Waukegan Road traffic signal is planned for the end of this week, pending contractor availability. Once completed, the contractor will complete the remaining sidewalk work along Waukegan Rd. The final roadway surface placement will be coordinated with other locations in around 2-3 weeks.
 
Elder Lane
Next week (the week of August 2nd) the contractor’s underground team will return to perform some additional storm sewer and water service improvements. The storm sewer improvements will work in conjunction with the new curb which is planned to be installed in the next 2-3 weeks.
 

Reminder that trash collection at all locations has been rescheduled for early pickup, starting at 6:30am. This is in an effort to avoid any conflicts with the construction crews.

Jul 27

[ARCHIVED] Construction Update: Week of July 26

The original item was published from July 27, 2021 7:32 AM to July 27, 2021 3:30 PM

Ambleside, Dimmeydale, and Windcrest
Directional boring for street light conduit is planned to begin in the next couple weeks, pending contractor availability. The final roadway surface placement will be coordinated with other locations and the completion of the street light work in around 2-3 weeks.    
Greenwood Avenue
Detector loops for Waukegan Road traffic signal is planned for the end of this week, pending contractor availability. Once completed, the contractor will complete the remaining sidewalk work along Waukegan Rd. The final roadway surface placement will be coordinated with other locations in around 2-3 weeks.
 
Elder Lane
Next week (the week of August 2nd) the contractor’s underground team will return to perform some additional storm sewer and water service improvements. The storm sewer improvements will work in conjunction with the new curb which is planned to be installed in the next 2-3 weeks.
 

Reminder that trash collection at all locations has been rescheduled for early pickup, starting at 6:30am. This is in an effort to avoid any conflicts with the construction crews.