The original item was published from November 18, 2019 7:12 AM to November 18, 2019 7:14 AM
In addition to the items noted below, pavement markings and minor punch list items remain at all locations.
_______________________
Berkeley Court: ACTIVE 99% complete
Paving completed on Friday 11/8. Minor parkway restoration remains.
Birchwood Ave.: 100% complete
Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete
Meadow Lane: ACTIVE 99% complete
Driveway restoration remains.
Rosemary Terrace: ACTIVE 99% complete
Minor parkway restoration remains. Placement of permanent pavement marking near Rosemary and Deerfield Road to be completed as weather permits.
Warrington Road: ACTIVE 95% complete
Mainline paving completed on Saturday 11/9. The paving contractor anticipates completing the remaining final paving near intersections this week as weather permits.
Wilmot Road (Greenwood to North Ave): ACTIVE 99% complete
Minor parkway restoration remains.
Woodland Subdivision: ACTIVE 90% complete
Final paving taking place today. Contractor will return for driveway restoration, minor parkway restoration, and pavement markings as weather permits.
The original item was published from November 18, 2019 7:12 AM to November 18, 2019 7:14 AM
In addition to the items noted below, pavement markings and minor punch list items remain at all locations.
_______________________
Berkeley Court: ACTIVE 99% complete
Paving completed on Friday 11/8. Minor parkway restoration remains.
Birchwood Ave.: 100% complete
Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete
Meadow Lane: ACTIVE 99% complete
Driveway restoration remains.
Rosemary Terrace: ACTIVE 99% complete
Minor parkway restoration remains. Placement of permanent pavement marking near Rosemary and Deerfield Road to be completed as weather permits.
Warrington Road: ACTIVE 95% complete
Mainline paving completed on Saturday 11/9. The paving contractor anticipates completing the remaining final paving near intersections this week as weather permits.
Wilmot Road (Greenwood to North Ave): ACTIVE 99% complete
Minor parkway restoration remains.
Woodland Subdivision: ACTIVE 90% complete
Final paving taking place today. Contractor will return for driveway restoration, minor parkway restoration, and pavement markings as weather permits.
The original item was published from November 18, 2019 7:12 AM to November 18, 2019 7:14 AM
In addition to the items noted below, pavement markings and minor punch list items remain at all locations.
_______________________
Berkeley Court: ACTIVE 99% complete
Paving completed on Friday 11/8. Minor parkway restoration remains.
Birchwood Ave.: 100% complete
Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete
Meadow Lane: ACTIVE 99% complete
Driveway restoration remains.
Rosemary Terrace: ACTIVE 99% complete
Minor parkway restoration remains. Placement of permanent pavement marking near Rosemary and Deerfield Road to be completed as weather permits.
Warrington Road: ACTIVE 95% complete
Mainline paving completed on Saturday 11/9. The paving contractor anticipates completing the remaining final paving near intersections this week as weather permits.
Wilmot Road (Greenwood to North Ave): ACTIVE 99% complete
Minor parkway restoration remains.
Woodland Subdivision: ACTIVE 90% complete
Final paving taking place today. Contractor will return for driveway restoration, minor parkway restoration, and pavement markings as weather permits.