Weekly Project Update - June 23

Posted on June 23, 2019 at 11:23 AM by Tyler Dickinson

Anticipated Schedule for Next Week:

RJ Underground will resume installation of new water main via directional drilling operations on Woodland Drive from Oakwood Place to Crabtree Lane.

RJ Underground will continue pot-holing existing utilities from Crabtree Lane to Stratford Road.

Percentage Complete: 11%

Neighborhood Impacts:

Construction operations will necessitate daily lane closures during working hours which may result in delays to local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the Woodland Subdivision Water Main Project.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.