2019 Woodland Watermain Project

Click here to view the complete project details including scope and locations.

View All Posts

Jun 07

Woodland WM Project Update - June 7

Posted on June 7, 2019 at 3:51 PM by Tyler Dickinson

Work Completed:

The contractor installed temporary erosion control measures and temporary tree protection fence on Woodland Drive from Wilmot Road to Hawthorne Place.

Underground crews started directional drilling operations of the new water main on Woodland Drive from Oakwood Place to Wilmot Road.


Issues Encountered:
No issues to note.

Anticipated Schedule for Next Week:

The boring contractor will continue and finish the installation of new water main via directional drilling operations from Crabtree Lane to Wilmot Road.

Percentage Complete: 7%

Neighborhood Impacts:

Construction operations will require daily lane closures during working hours, which may result in delays to local vehicular traffic. Please be cautious through the construction work zone, and residents shall be alert for workers and construction equipment. We will continue to provide notice to affected residents and stakeholders as construction progresses.

The Village appreciates your effort in helping to complete this improvement. If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 847-317-2490 and request to speak with someone regarding the Woodland Subdivision Water Main Project.