2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Jun 01

Update for Week of 6/3: Work Continues on Warrington, Cranshire, Montgomery plus Meadow Lane

Posted on June 1, 2019 at 10:48 AM by John Guccione

PLEASE READ THE ENTIRE NOTICE, as it provides status and maps for various locations.

Warrington Road  
(Water shut down on Monday, June 3rd)

Underground work continues with a planned interruption of water service on Monday June 3rd from 10 am through 2 pm. This water shut down is the result of a water valve which requires replacement (indicated by red X on map below). Residents to be impacted by Monday's water shut down are highlighted on the map below and were notified on Saturday June 1st using water department "Door Hangers".   Storm sewer work will continue through the week.

VALVE-replace-6-3-2019

Castlewood, Cranshire, Montgomery, Chatam, Pear Tree & Village Green: 
(Driveway Access Impacts on Monday, June 3rd)

On Monday, the contractor will continue to remove and replace curbs and sidewalks. This work will impact driveway access beginning on Monday at the locations listed below. Impacted residents were notified on Friday, May 31st by way of physical notices posted at their properties.

  • Montgomery Drive (entire west side)
  • Cranshire Court (entire north side)
  • Chatham Court  (spot repairs to areas marked with pink paint)
  • Peartree Road (spot repairs to areas marked with pink paint)
  • Village Green (spot repairs to areas marked with pink paint)
400-CASTLEWOOD-3rd-PHASE

Meadow Lane
(Driveway Access Impacts on Tuesday, June 4th)

On Tuesday, the contractor will begin removing and replacing curbs on the south side of Meadow Lane. This work will impact driveway access beginning on Tuesday. Impacted residents were notified on Saturday June 1st by way of physical notices posted at their properties.

800-MEADOW-concrete-PH1