2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

May 19

Update for Week of 5/20: Concrete Pour on Castlewood, Storm Sewer Install on Warrington.

Posted on May 19, 2019 at 3:57 PM by John Guccione

Castlewood, Cranshire, Pear Tree & Village Green:
The contractor will begin removing curb and sidewalk beginning Monday May 20th on the west side of Castlewood and the south side of Cranshire. Curb is planned to be placed on Wednesday. Impacted residents will not have access to their driveways for 5-7 days, beginning Wednesday at 7am. Impacted residents were notified on Friday May 17th by way of physical notices posted at their property.

Warrington Road:
Storm sewer installation will continue on the north end of Warrington next week. This operation will limit vehicular access to Warrington Road from Woodvale Ave to Cumnor Court.  Access will be allowed for school buses and for those whom reside within the aforementioned limits.  All others should select alternate routes during daytime operations.