Work Resumes Thursday September 20th on Elmwood & Crabtree

Posted on September 19, 2018 at 2:44 PM by John Guccione

Curb Removal will take place tomorrow on Elmwood in preparation for concrete curb replacement on Friday.  Excavation will also take place tomorrow on Crabtree in preparation for the placement of depressed curb on Crabtree on Monday.

Once excavation is completed, driveway access will be maintained at both locations utilizing “stone access driveways” until the day your locations concrete pour. Once concrete is placed, residents will not be able to access their driveways until the concrete cures.

Physical notifications were distributed today which provide more details specific to each location.