There will be a planned interruption of water service on Monday on Meadow Lane Ave that will impact 23 homes between 9:30 AM and 2 PM. Impacted residents have been notified by use of blue door hangers. Directional boring operations have been completed in Woodland Park. Water main installation will take place next week on Crabtree. 

Early waste collection begins next week on Elmwood and Crabtree (not Meadow)
In conjunction with the Village’s street reconstruction projects, the Village has worked with Waste Management to help ensure that the projects (ongoing and upcoming) do not affect the weekly garbage collection. To do this, Waste Management will be performing all future waste collections on Tuesdays between the hours of 6 AM and 7 AM.  This change will begin this Tuesday August 7, 2018. This will require residents to have their waste ready for pick up late Monday night or by 6 AM on Tuesday mornings. This revised collection time is in efforts to avoid access difficulties during active construction hours.

Byron Court
Base course paving was completed this past week. This location awaits parkway restoration and final surface paving which will take place in 3-5 weeks.

Oxford Road
Asphalt base paving is completed. Utility structures have been adjusted so that Public Works may have access to utilities and in preparation for final surface paving which may take place in 2-4 weeks.

Bristol Estates Subdivision & Bristol Drive
This location is 100% completed.  Only minor restoration remains. Any landscaping deficiencies will be addressed towards the end of the construction season.

Osterman Ave & Somerset Ave
Paving is complete on both Osterman and Somerset. Restoration is also complete on Osterman. However, Somerset restoration is in progress and is not complete yet.