Project Update for Week of 7/30/2018

Posted on July 27, 2018 at 10:17 AM by John Guccione

Byron Court
Underground sewer installation has been completed. Pavement removal will begin on Monday and paving is anticipated to take place towards the end of next week

Crabtree, Meadow and Elmwood
Directional boring operations will take place next week through Woodland Park, with boring pits existing on Crabtree, Meadow and Elmwood. Open cut installation of the new water main on Crabtree will take place the following week.

Oxford Road
Asphalt base paving is completed. Utility structures have been adjusted so that Public Works may have access to utilities and in preparation for final surface paving which may take place in 2-4 weeks.

Bristol Estates Subdivision & Bristol Drive
This location is 100% completed.  Only minor restoration remains. Any landscaping deficiencies will be addressed towards the end of the construction season.

Osterman Ave & Somerset Ave
Paving is complete on both Osterman and Somerset. Restoration is also complete on Osterman. However, Somerset restoration is in progress and is not complete yet.