Somerset & Osterman Curb Pour Tomorrow

Posted on May 8, 2018 at 12:17 PM by John Guccione

The curb pour that was initially planned for this Thursday has been revised to Wednesday (tomorrow). 

The temporary stone driveway will be removed tomorrow morning at 7:30 AM. At which point the new curb will be poured. After the curb has been poured, residents whose driveways are impacted will not be able to access their driveways until the concrete cures (3-5 Days) and passes strength tests.  