Oxford Road
Materials needed for underground storm sewer repairs will be delivered this week with underground work to begin on Thursday or Friday of this week.  This work may result in road closures of small portions of Oxford Rd.  Local traffic will be diverted to adjacent local roads. Access will be granted to those who reside within the limits and to emergency vehicles. 

Bristol Estates Subdivision, Bristol Drive, Kenmore Ave & Central Ave
Concrete curb and sidewalk repairs have been completed at the Kenmore and Central Ave locations. The contractor is working to complete concrete work in the Bristol Estates subdivision and on Bristol Drive. 

Milling of the top 2" to 3" of surface pavement began today on Kenmore and Central Ave. Milling operations will begin tomorrow in the Bristol Estates subdivision and on Bristol Drive. Milling is performed in preparation for the placement of leveling binder course which is scheduled to place the week of May 7th.  Surface course paving will follow within the next 2-3 week after the level binder installation.

Both the pavement removal and paving operations will include heavy truck traffic and may present minor access delays to residential driveways and to through traffic. During this time and if possible, please avoid the construction operations and utilize the side roads. All driveways will be accessible at the completion of the work day.