Brierhill Road Project Construction Update – 5/18/2017

A COUPLE REMINDERS

  • PLEASE REMIND ALL LANDSCAPERS AND CONTRACTORS TO COME OUTSIDE OF CONSTRUCTION HOURS AS PREVIOUSLY DISCUSSED.
  • DO NOT REMOVE UTILITY FLAGS FROM YOUR FRONT YARD. THESE ARE PLACED TO HELP PROTECT THE UTILITIES AND THE WORKERS WORKING AROUND THEM. PLEASE PASS THIS ALONG TO YOUR LANDSCAPERS.

LAST WEEK

The contractor completed the water services installation this week.

SCHEDULE

Next week, the contractor will begin the sanitary sewer point repairs which will include the replacement of the sewer pipes at locations where the existing pipe is broken or has nearly collapsed. As this is a repair to an existing line, the contractor will be required to dig along the pipe which at times could be in or around landscaped areas. This will be similar to the water services installations in that the contractor does not have the option of digging elsewhere but will do what they can to help minimize the impacts to the surrounding areas.