View All Posts

May 15

Construction Update - 5/15/2017

Posted on May 15, 2017 at 1:32 PM by Tyler Dickinson

Deerfield Logo small

Village of Deerfield

Brierhill Road Project Construction Update – 5/15/2017

A COUPLE REMINDERS

  • PLEASE REMIND ALL LANDSCAPERS AND CONTRACTORS TO PLEASE COME OUTSIDE OF CONSTRUCTION HOURS AS PREVIOUSLY DISCUSSED.
  • DO NOT REMOVE UTILITY FLAGS FROM YOUR FRONT YARD. THESE ARE PLACED TO HELP PROTECT THE UTILITIES AND THE WORKERS WORKING AROUND THEM. PLEASE PASS THIS ALONG TO YOUR LANDSCAPERS AS WELL.

LAST WEEK

The contractor continued with water services installation and to date, has completed roughly half of the new water services.

SCHEDULE

This week, the contractor will continue to install water services. Residents will receive a notice of water impact the day before any impact is expected. Also, immediately prior to any impact, the contractor will verbally notify those that are home of the impact so that it is not a surprise to anyone.

This work, at times, will require excavation across the entire roadway, causing traffic delays. Depending on the location of a property’s shut off valve, or b-box, the excavation may also extend into a parkway area. This work was discussed at length during the preconstruction meeting held with the residents in March. Please see the below diagram for a visual aid.   

Brierhill Water Service

Please be advised that the information communicated here is a forecast of proposed operations, which may change due to contractor availability and/or weather conditions.