Construction Forecast for the week of 5/1/2017

Posted on April 28, 2017 at 12:30 PM by John Guccione

This construction forecast is for the week of May 1, 2017.

PINE STREET CONSTRUCTION FORECAST
Next week the contractor will begin removing the existing pavement and begin to fine-grade the sub-base in preparation for placement of the new roadway. The contractor will also continue placing topsoil in parkway areas in preparation for placement of sod which will take place in the next 1-2 weeks.

FAIR OAKS AVE CONSTRUCTION FORECAST
On Fair Oaks, the contractor completed the north side curb and gutter and will complete the south side next week.

GARAND DRIVE CONSTRUCTION FORECAST
It is expected that work on Garand Drive will begin in the next couple weeks and work on Wincanton in the next two months.