Construction Update for Week of June 1, 2020

Posted on June 1, 2020 at 10:44 AM by John Guccione

The below update provides a forecast of construction operations planned for the week of June 1st.  Please note that this forecast is subject to change due to weather and contractor availability.

PROJECT LOCATIONS LISTED IN ALPHABETICAL ORDER

Dartmouth Ave 
(Wilmot To Mallard.Including Pembroke and Circle Courts
Resulting from pavement removals beginning last Friday, rather than Thursday, Monday presents Day#2 of pavement removals. Whereas, on Friday (day 1 of pavement removals) only the required depth of pavement was removed, so as to allow safe access to the road without leaving a center line drop off over the weekend. This week, during pavement removals (Monday) and sub-base preparation (Tuesday through Thursday) minimal access delays may be experienced.  Once pavement removal and/or sub-base preparation walks past your location, the contractor quickly installs stone ramps allowing access.  *Paving is planned for for Friday, pending sub-contractor availability.

ORANGE highlighted area represents project limits. 
DARTMOUTH-pavement-removal

Hillside Ave (Hazel to Somerset)
Curb removal will take place along the west side of the roadway in preparation for curb placement planned for Wednesday and Thursday. Physical notices will be hand delivered to residents prior to driveway access impacts. Upon completing the west side curb, the contractor will return the following week to remove and replace the east side.  Additional notice will proceed any driveway access impacts.

Knollwood Rd 
(Warwick to Margate) plus Westgate
Project completed.   Only punch list items remain.   **WATER MAIN BREAK experienced over the weekend (on May 30) within the intersection of Knollwood and Westgate was not project related. However, ALamp will patch this section of pavement on Tuesday.

Knollwood Rd 
(Margate to Kingston) plus Margate Terrace 
Project completed.   Only punch list items remain.  

Linden Ave (Stratford to Chestnut)
Curb removal will take place along the north side of the roadway in preparation for curb placement planned for Wednesday and Thursday. Physical notices will be hand delivered to residents prior to driveway access impacts. Upon completing the north side curb, the contractor will return the following week to remove and replace the south side.  Additional notice will proceed any driveway access impacts.

CORONAVIRUS NOTICE
The Village’s infrastructure construction projects fit under an exemption per the Governor’s Stay at Home order. Outdoor activities, like construction projects, generally will provide for good social distancing that poses little risk of transmission, but it still is important to ensure the ability to wash or sanitize hands and take other precautions. Village and contractor personnel will continue to practice safe social distancing and sanitation efforts during the construction.

If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at 
847-317-2490 and request to speak with someone regarding the 2020 Street Rehab Project.