Construction Update for Week of 5/4/2020

Posted on May 4, 2020 at 3:30 PM by Tyler Dickinson

The below update provides a forecast of construction operations planned for the week of May 4, 2020. Please note that this forecast is subject to change due to weather.

PROJECT LOCATIONS LISTED IN ALPHABETICAL ORDER

Dartmouth Ave
(Wilmot Rd. To Pine St.) Including Pembroke and Circle Courts
The contractor will begin installation of new curb and sidewalk on the north side of Dartmouth beginning tomorrow (Tuesday) and will continue through the rest of the week until that side is complete. In the coming weeks, the contractor will turn their attention to the south side and preparing that side for new curb and sidewalk.

Knollwood Rd
(Margate to Kingston)
Last week, the contractor was able to complete the grinding of the existing pavement in preparation for the new asphalt.

The contractor anticipates paving the first layer of asphalt on this block on Thursday.

Knollwood Rd
(Warwick to Margate)
Last week, the contractor was able to complete the removal of the existing pavement and began grading the roadway base in preparation for the new asphalt. They also began preparing parkways for the placement of sod in disturbed areas.

This week, the contractor has started installing sod on Monday. The contractor will continue to fine grade the roadway base and plans to pave the base layer of asphalt (all but the top 2”) on Wednesday.

Margate Terrace and Westgate Road
(Warrington to Kenton)
Last week, the contractor was able to complete the removal of the existing pavement and began grading the roadway base in preparation for the new asphalt. They also began preparing parkways for the placement of sod in disturbed areas.

This week, the contractor will continue to fine grade the roadway base and plans to pave the base layer of asphalt (all but the top 2”) on Wednesday.

CORONAVIRUS NOTICE
The Village’s infrastructure construction projects fit under an exemption per the Governor’s Stay at Home order. Outdoor activities, like construction projects, generally will provide for good social distancing that poses little risk of transmission, but it still is important to ensure the ability to wash or sanitize hands and take other precautions. Village and contractor personnel will continue to practice safe social distancing and sanitation efforts during the construction.


If you have any questions or require special assistance during construction, please contact the Village of Deerfield Engineering Department at