2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Dec 02

Final Street Rehab Update 12/2/2019

Posted on December 2, 2019 at 8:55 AM by John Guccione

 

All locations are now considered 100% complete with only punch list items remaining.  Punch list items include work such as: clean up, parkway restoration, brick replacement and a few remaining driveway approach repairs. In addition to the aforementioned items, the contractor will also be cleaning out drainage structures and other public utility structures, ensuring they are clear of debris.

Village wide pavement marking
is planned to take place tomorrow and through the end of the week, as weather permits.  Cross walks and stop bars will be placed with minimal impacts to the travelling public. Please exercise patience and drive carefully in the proximity of this operation.

This will be the final construction update for the 2019 Street Rehab Project.
The Village thanks all of our residents for their patience and understanding through this past construction season. Residents with any remaining questions or concerns relative to the 2019 Street Rehab Project may contact the Engineering Department at 847-317-2490.

Please note that the project has a warranty period of 1 year. Village staff will inspect all locations in the Spring of 2020 to address any items remaining from the 2019 season, and will also inspect again in August of 2020 to identify any warranty items.
_______________________

Berkeley Court:  100% complete
Birchwood Ave:  100% complete
Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete
Meadow Lane: 100% complete
Rosemary Terrace: 100% complete
Warrington Road 100% complete
Wilmot Road: 100% complete
Woodland Subdivision:100% complete