Update for week of November 25

Posted on November 25, 2019 at 7:21 AM by John Guccione

Status provided per location, sorted in alpha order.   In addition to the items provided below, the contractor will also be cleaning out drainage structures and other public utility structures, ensuring they are clear of debris.

_______________________
Berkeley Court:  
ACTIVE  99% complete 

Minor parkway restoration remains.

Birchwood Ave.:   100% complete

Castlewood Ln., Cranshire, Chatham, Peartree & Village Green: 100% complete


Meadow Lane: ACTIVE  99% complete 
Minor parkway restoration and some driveway restoration remains. 

Rosemary Terrace: 
ACTIVE 99% complete 
Minor parkway restoration remains. Placement of permanent pavement marking in planned for this week near Rosemary and Deerfield Road (to be completed as weather permits).

Warrington Road ACTIVE 99% complete 
Surface paving completed last week. Minor parkway restoration and some driveway restoration remains. 

Wilmot Road (Greenwood to North Ave): ACTIVE  99% complete 

Minor parkway restoration remains.

Woodland SubdivisionACTIVE 99% complete 
Surface paving completed last week. Minor parkway restoration and some driveway restoration remains.