2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Nov 11

Update for Week of 11/11

Posted on November 11, 2019 at 8:17 AM by John Guccione

(PROJECT LOCATIONS LISTED BY ALPHA)  
In addition to the items noted, pavement marking and punch list items remain at all locations.
_______________________
Berkeley Court:  
ACTIVE  99% complete 

Paving completed on Friday 11/8. Minor parkway restoration remains.

Birchwood Ave:   100% complete
Restoration has been completed. 

Castlewood, Cranshire, Chatham, Peartree & Village Green: 100% complete

Restoration has been completed. 

Meadow Lane: ACTIVE  99% complete 

Restoration has been completed. 

Rosemary Terrace: 
ACTIVE 99% complete 
Minor parkway restoration remains. Placement of permanent pavement marking is planned for 1-2 weeks near Rosemary and Deerfield Road (as weather permits).

Warrington ACTIVE 95% complete 
Mainline paving completed on Saturday 11/9. The paving contractor is standing by to pave the remaining intersections once weather permits. Minor parkway restoration remains. 

Wilmot Road (Greenwood to North Ave) ACTIVE  99% complete 

Minor parkway restoration remains. Placement of permanent pavement marking is planned for 1-2 weeks (as weather permits).

Woodland SubdivisionHawthorne, Oakwood, Woodbine & Woodland ACTIVE 90% complete 
Leveling binder paving was completed on Friday, November 8th. Structure adjustments completed on Saturday, November 9th.   The paving contractor is standing by to place the final asphalt surface course once weather permits.