2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Oct 28

Update for Week of 10/28

Posted on October 28, 2019 at 9:22 AM by John Guccione

(PROJECT LOCATIONS LISTED BY ALPHA)

Berkeley Court:  
ACTIVE  90% complete 

Surface paving is planned for Monday & Tuesday of this week. Residents should note that the contractor will apply prime coat material which will require motorists to travel slowly. See fresh oil statement provided at the end of this update.


Birchwood Ave:   ACTIVE 98% complete 
Restoration has been completed. Punch list items remain.

Castlewood, Cranshire, Chatham, Peartree & Village Green: 100% complete

Restoration has been completed. Punch list items remain.

Meadow Lane: ACTIVE  90% complete 

Surface paving underway on Meadow Lane (active on Monday morning). 

Rosemary Terrace: 
ACTIVE 98% complete 
Paving of the final surface course has been completed. Parkway restoration to be completed this week at remaining areas (before Halloween). Placement of permanent pavement marking is planned for 1-2 weeks near Rosemary and Deerfield Road.

Warrington ACTIVE 95% complete 
Adjustments to underground structures will take place today in preparation for surface course which is planned for Tuesday and Wednesday of this week.  On Tuesday, the contractor will place reflective crack-control fabric prior to placing the final layer of hot mix asphalt. This will require the temporary closure of Warrington from Warwick to Kingston Terrace  (while the material is being placed between 9 a.m. & 11 a.m.). Only local Traffic will be permitted on the fabric, all other should select an alternative route.

REFLECTIVE-CRACK-CONTROL


Wilmot Road (Greenwood to North Ave) ACTIVE  90% complete 

Surface paving is planned for Monday & Tuesday of this week. Residents should note that the contractor will apply prime coat material which will require motorists to travel slowly. See fresh oil statement provided at the end of this update.

Woodland SubdivisionHawthorne, Oakwood, Woodbine & Woodland ACTIVE 85% complete 
On Tuesday the contractor will perform subsurface patching to repair failures in the pavement (prior to resurfacing). The contractor will also lower frames and lids to underground utilities in preparation for pavement resurfacing.  Paving of the first layer of asphalt is planned to begin this Wednesday (through the end of the week).
___________________

fresh-oil

Please be aware that signs stating “Fresh Oil” may be observed throughout the time period when asphalt paving will occur. The use of fresh oil helps different layers of asphalt to adhere to one another providing a longer lasting final product. Residents should be mindful of driving through fresh oil. If a detour is not in place and motorists must drive through fresh oil, please drive slowly. Driving at higher speeds through fresh oil may cause the material to adhere to the undercarriage and/or fenders of the car, which can be difficult and costly to remove.