2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Oct 25

Paving Schedule for Week of 10/28 (Paving Meadow, Wilmot & Berkeley on Monday)

Posted on October 25, 2019 at 2:12 PM by John Guccione

Paving is planned for various locations next week within the Village. 

PAVING SCHEDULE for Monday 10/28/2019
Meadow Ln: 
Paving on Monday at 8 a.m. until completed. Driveway repairs will take place this Saturday in prep for paving Monday.  MEADOW CLOSED MONDAY 8 am to 11 am 
Wilmot Rd & Berkeley Ct: Paving will begin on Monday at around 11 a.m. (upon completion of paving Meadow).

PAVING SCHEDULE for Tuesday 10/29/2019 
Margate Terrace:  Paving on Tuesday at 7:30 a.m. until completed.
Warrington Road: Paving on Tuesday upon completion of Margate. (Final road patching and sewer adjustments will take place on Monday in prep for paving Tuesday.)

PAVING SCHEDULE for Wednesday (through end of the week) 10/30/2019 
Woodland Subdivision: Woodland, Oakwood, Hawthorne & Woodbine Final road patching and sewer adjustments will take place on Monday and Tuesday in prep for paving which will begin Wednesday.
___________________________

Paving operations will include heavy truck traffic and will present major delays to through traffic and minor delays to driveway access. During this time and if possible, please avoid the construction operations and utilize adjacent roadways. All driveways will be accessible at the completion of the work day.

fresh-oil

Please be aware that signs stating “Fresh Oil” may be observed throughout the time period when asphalt paving will occur. The use of fresh oil helps different layers of asphalt to adhere to one another providing a longer lasting final product. Residents should be mindful of driving through fresh oil. If a detour is not in place and motorists must drive through fresh oil, please drive slowly. Driving at higher speeds through fresh oil may cause the material to adhere to the undercarriage and/or fenders of the car, which can be difficult and costly to remove.

*Schedule is subject to change, as paving operations are 
dependent upon dry weather conditions.