2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Oct 07

Update for Week of 10/7

Posted on October 7, 2019 at 8:21 AM by John Guccione

(PROJECT LOCATIONS LISTED BY ALPHA)

Berkeley Court:  
ACTIVE  90% complete 

Paving of leveling binder has been completed (1 of 2 layers). Over the next 1-2 weeks the contractor will perform restoration of parkway ares in preparation for surface course paving to be placed in 2-4 weeks (in coordination with the Woodland Subdivision Project).

Birchwood Ave:   ACTIVE 98% complete 

Paving of the final surface course has been completed. Only restoration to parkway areas and punch list items remain.  Parkway restoration planned for this week.

Castlewood, Cranshire, Chatham, Peartree & Village Green: 100% complete

Restoration has been completed. Punch list items remain.

Meadow Lane: ACTIVE  90% complete 

Paving of leveling binder has been completed (1 of 2 layers). Over the next 1-2 weeks the contractor will perform restoration of parkway ares in preparation for surface course paving to be placed in 2-4 weeks (in coordination with the Woodland Subdivision Project).

Rosemary Terrace: 
ACTIVE 98% complete 

Paving of the final surface course has been completed. Only restoration to parkway areas and punch list items remain.  Parkway restoration planned for this week.


Warrington ACTIVE 95% complete 
Prior to paving, our leak detection service found a leak water leak which will be repaired this week at Warrington and Essex. Final road patches will take place towards the end of this week. Adjustments to underground structures will also take place in preparation for surface course to be coordinated with all remaining locations in the next 2-3 weeks. Additional notice will precede.

Wilmot Road (Greenwood to North Ave) ACTIVE  90% complete 

Paving of leveling binder has been completed (1 of 2 layers). Over the next 1-2 weeks the contractor will perform restoration of parkway ares in preparation for surface course paving to be placed in 2-4 weeks (in coordination with the Woodland Subdivision Project).

Woodland SubdivisionHawthorne, Oakwood, Woodbine & Woodland ACTIVE 80% complete 
Pouring of "spot repair" curb locations will begin Monday afternoon and will continue through the week. Televising of sanitary sewer lines have been completed. Televising of storm sewers will now begin to ensure no issues resulted from directional boring of water main and/or services. Once all televising is completed, ALamp's underground crew will return this Wednesday to remedy any issues discovered during televising. Once concrete and underground final repairs are completed, pavement grinding will follow in the next 1-2 weeks in preparation for roadway resurfacing.