Work Completed Last Week:

The contractor removed sidewalk and curb and gutter at various locations along the north side of Greenwood Ave. from Wilmot Rd. to Chestnut St.

Anticipated Schedule for upcoming weeks:

New concrete sidewalk and curbs will be installed on the north side of Greenwood Ave, west of Chestnut St. Once the sidewalk and curb have been completed and the sidewalk is open to pedestrian traffic, the contractor will begin with the roadway work.

This project has a contract completion date of October 31, 2019. 

Percentage Complete: 62%

Neighborhood Impacts:

At times, vehicles will not be able to pass the contractor’s work operations which may result in delays to local traffic. Caution should be practiced through the construction work zone and residents must be alert for workers and construction equipment.

The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.