Blog module icon

2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Sep 30

Update for Week of 9/30 (Paving Birchwood & Rosemary on Tuesday)

Posted on September 30, 2019 at 9:02 AM by John Guccione

THIS WEEKS HIGHLIGHTS
Surface Paving on Tuesday, October 1st for Birchwood Ave & Rosemary Ter.
Rosemary Terrace:
Paving on Tuesday at 7:30 a.m. until completed.
Birchwood Avenue: Will begin on Tuesday upon completion of paving Rosemary.
________________________________________
(PROJECT LOCATIONS LISTED BY ALPHA)

Berkeley Court:  
ACTIVE  90% complete 

Paving of leveling binder was completed last week (1 of 2 layers). Over the next 2 weeks the contractor will perform restoration of driveway approaches and parkway ares in preparation for surface course paving to be placed in 4-5 weeks (in coordination with the Woodland Subdivision Project).

Birchwood Ave: SURFACE PAVING ON TUESDAY 95% complete 

Paving of the final surface course will take place on Tuesday, October 1st. During tomorrow’s operation the contractor will place 1.75 inches of hot mix asphalt surface. Once this layer of asphalt has time to cool, traffic will be permitted to travel across it (1-2 hours after placement).

Paving operations will include heavy truck traffic and will present major delays to through traffic and minor delays to driveway access. During this time and if possible, please avoid the construction operations and utilize adjacent roadways. All driveways will be accessible at the completion of the work day.


Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 100% complete

Restoration has been completed. Punch list items remain.

Meadow Lane: ACTIVE  90% complete 

Paving of leveling binder was completed last week (1 of 2 layers). Over the next 2 weeks the contractor will perform restoration of driveway approaches and parkway ares in preparation for surface course paving to be placed in  2-4 weeks.

Rosemary Terrace: SURFACE PAVING ON TUESDAY  95% complete 

Paving of the final surface course will take place on Tuesday, October 1st. During tomorrow’s operation the contractor will place 1.75 inches of hot mix asphalt surface. Once this layer of asphalt has time to cool, traffic will be permitted to travel across it (1-2 hours after placement). 

Paving operations will include heavy truck traffic and will present major delays to through traffic and minor delays to driveway access. During this time and if possible, please avoid the construction operations and utilize adjacent roadways. All driveways will be accessible at the completion of the work day.

Warrington 95% complete 
The remaining underground work was completed this weekend on Warrington. Final road patches and concrete curb repairs will take place towards the end of this week. Adjustments to underground structures will also take place in preparation for surface course to be coordinated with all remaining locations in the next 2-3 weeks. Additional notice will precede.

Wilmot Road (Greenwood to North Ave) ACTIVE  90% complete 
Paving of leveling binder was completed last week (1 of 2 layers). Over the next 2 weeks the contractor will perform restoration of driveway approaches and parkway ares in preparation for surface course paving to be placed in 4-6 weeks (in coordination with the Woodland Subdivision Project).

fresh-oil

Please be aware that signs stating “Fresh Oil” may be observed throughout the time period when asphalt paving will occur. The use of fresh oil helps different layers of asphalt to adhere to one another providing a longer lasting final product. Residents should be mindful of driving through fresh oil. If a detour is not in place and motorists must drive through fresh oil, please drive slowly. Driving at higher speeds through fresh oil may cause the material to adhere to the undercarriage and/or fenders of the car, which can be difficult and costly to remove.