View All Posts

Sep 30

Greenwood Weekly Project Update - September 30

Posted on September 30, 2019 at 8:28 AM by Tyler Dickinson

September 30, 2019


Work Completed Last Week:

The contractor completed the concrete sidewalk and curb and gutter installation along the south side of Greenwood Ave. from Wilmot Rd. to Chestnut St.

Anticipated Schedule for upcoming weeks:

New concrete sidewalk and curbs installation on the north side of Greenwood Ave, west of Chestnut St will begin this week after the Holiday. Once the sidewalk and curb has been completed and the sidewalk is open to pedestrian traffic, the contractor will begin with roadway work. 

Percentage Complete: 60%

Neighborhood Impacts:

At times, vehicles will not be able to pass the contractor’s work operations which may result in delays to local traffic. Caution should be practiced through the construction work zone and residents must be alert for workers and construction equipment.

The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.