Woodland WM Project Update - September 23

Posted on September 23, 2019 at 7:49 AM by Tyler Dickinson

September 23, 2019


Work Completed Last Week:

The underground contractor completed the remaining water main connections last week and therefore, has completed the water main installation in the subdivision. The contractor worked to demobilize various materials and equipment throughout the project limits.

Anticipated Schedule for This Week:

T
he contractor will work to grade parkways that were disturbed during the water main project and also continue to demobilize.

Now that the water main project is substantially complete, the street rehabilitation project will begin. This project will repair impacted curbs, perform roadway patches, and resurface the roads within the subdivision. In order to receive updates for this upcoming work, residents are encouraged to sign up for the 2019 Street Rehabilitation Project Blog via the Village Website. 


Percentage Complete: 77%

Neighborhood Impacts:

Construction operations will necessitate daily lane closures during working hours which may result in delays to
local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.


The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.