2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Sep 23

Update for Week of 9/23

Posted on September 23, 2019 at 7:59 AM by John Guccione

(PROJECT LOCATIONS LISTED BY ALPHA)

Berkeley Court:  
ACTIVE  90% complete 

Paving of leveling binder was completed last week (1 of 2 layers). Over the next 2 weeks the contractor will perform restoration of driveway approaches and parkway ares in preparation for surface course paving to be placed in 4-6 weeks (in coordination with the Woodland Subdivision Project).

Birchwood Ave: AWAITING SURFACE PAVING 95% complete 
Adjustments to underground structures will take place this week in preparation for surface course to be coordinated with all remaining locations in the next 2-4 weeks. Additional notice will precede.

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 100% complete
Restoration has been completed. Punch list items remain.

Meadow Lane: ACTIVE  90% complete 
Paving of leveling binder was completed last week (1 of 2 layers). Over the next 2 weeks the contractor will perform restoration of driveway approaches and parkway ares in preparation for surface course paving to be placed in  2-4 weeks.

Rosemary Terrace: ACTIVE  80% complete 

Spot repairs to concrete and removal of the old roadway was performed last week. The contractor will pave Rosemary Ave using one layer (lift) of surface course asphalt in 2-4 weeks. Additional notice will precede.

WarringtonAWAITING SURFACE PAVING 95% complete 
Restoration of driveways north of Warwick was completed this past weekend. Some final underground work will take place just south of Warwick on Warrington this week. Adjustments to underground structures will take place this week in preparation for surface course to be coordinated with all remaining locations in the next 2-4 weeks. Additional notice will precede.

Wilmot Road (Greenwood to North Ave) ACTIVE  90% complete 
Paving of leveling binder was completed last week (1 of 2 layers). Over the next 2 weeks the contractor will perform restoration of driveway approaches and parkway ares in preparation for surface course paving to be placed in 4-6 weeks (in coordination with the Woodland Subdivision Project).