2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Sep 16

Update for Week of 9/16

Posted on September 16, 2019 at 7:38 AM by John Guccione

Berkeley Court:  ACTIVE  80% complete 
Pavement grinding was completed last Friday.  Paving is scheduled for this Thursday. On Thursday 9/19/2019 the contractor will place the first layer of (leveling) asphalt. Paving operations will result in delayed access to the roadway. Physical notices will be distributed that provide additional info. Once paving is completed, the contractor will spend 1-3 week preparing all locations for final surface paving.

Meadow Lane: ACTIVE  80% complete 
Pavement grinding was completed last Friday.  Paving is scheduled for this Friday. On Friday 9/20/2019 the contractor will place the first layer of (leveling) asphalt. Paving operations will result in delayed access to the roadway. Physical notices will be distributed that provide additional info. Once paving is completed, the contractor will spend 1-3 week preparing all locations for final surface paving.

Wilmot Road (Greenwood to North Ave) ACTIVE  80% complete 
Pavement grinding was completed this past Saturday.  Paving is scheduled for this Wednesday. On Wednesday 9/18/19 the contractor will place the first layer of (leveling) asphalt. Paving operations will result in delayed access to the roadway. Physical notices will be distributed that provide additional info. Once paving is completed, the contractor will spend 1-3 week preparing all locations for final surface paving.

Rosemary Terrace:
 ACTIVE 75% complete 
Pavement grinding was completed this past Saturday. On Wednesday an additional round of concrete removal and replacement will take place in preparation for paving on Friday. On Friday 9/20/2019 the contractor will place the first layer of (leveling) asphalt. Paving operations will result in delayed access to the roadway. Physical notices will be distributed that provide additional info. Once paving is completed, the contractor will spend 1-3 week preparing all locations for final surface paving.

Birchwood Ave: AWAITING SURFACE PAVING 90% complete 
Adjustments to underground structures will take place this week in preparation for surface course paving tentatively set for the week of September 23rd.

WarringtonAWAITING SURFACE PAVING 90% complete 
Driveway restoration will take place this week north of Warwick., Adjustments to underground structures will also take place this week in preparation for surface course paving the week of September 23rd.  Sod has been placed south of Warwick. Sod to be placed north of Warwick next week, pending completion of driveway approach restorations that will take place later this week.

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 99% complete
Brick paver restoration began this past Saturday and will continue through the week. Restoration of parkway areas has been completed. Punch list items remain.

***PLEASE NOTE THAT THIS IS A FORECAST OF THE OPERATIONS PLANNED FOR THE WEEK.   DATES ARE SUBJECT TO CHANGE, DEPENDENT UPON WEATHER & CONTRACTOR AVAILABILITY.