2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Sep 09

Update for Week of 9/9

Posted on September 9, 2019 at 8:48 AM by John Guccione

Berkeley Court:  ACTIVE  60% complete 
The depressed concrete curb will be poured on the south side of the street on Monday, September 9th. On Thursday afternoon, the contractor will return to grind the 2" surface to reveal the subsurface. Once the subsurface is revealed, patching of any subsurface failures will take place previous to placing the first layer of asphalt which is tentatively planned for September 19th.

Meadow Lane: ACTIVE  60% complete 
On Thursday morning, the contractor will return to grind the 2" surface to reveal the subsurface. Once the subsurface is revealed, patching of any subsurface failures will take place previous to placing the first layer of asphalt which is tentatively planned for September 19th.

Wilmot Road (Greenwood to North Ave)    ACTIVE 60% complete 
Two small drainage structures will be replaced on Wednesday and will complete underground repairs on Wilmot.  A third (smaller) phase of concrete will be performed Monday & Tuesday. Surface pavement grinding (2" depth) will take place on Friday. Once the subsurface is revealed, patching of any subsurface failures will take place previous to placing the first layer of asphalt which is tentatively planned for September 20th.

Rosemary Terrace:
  Concrete removal and replacement will take place on Tuesday in relation to a slight widening of the roadway at Deerfield Road, to allow the installation of a turn lane. The contractor will return on September 16th to grind the surface pavement in preparation for resurfacing.

Birchwood Ave: AWAITING SURFACE PAVING 80% complete 
Adjustments to underground structures will take place this week in preparation for surface course paving tentatively set for the week of September 23rd.

WarringtonAWAITING SURFACE PAVING 80% complete 
Driveway restoration will take place this week north of Warwick., Adjustments to underground structures will also take place this week in preparation for surface course paving the week of September 23rd.  Sod has been placed south of Warwick. Sod to be placed north of Warwick next week, pending completion of driveway approach restorations that will take place later this week.

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 99% complete
Restoration of parkway areas has been completed. Punch list items remain.