Berkeley Court:  ACTIVE  Possible Weather Delay today
This morning's curb pour may be delayed due to rain. Radar shows a break in the weather, which may still allow curb to be placed this afternoon. If the curb is not poured today, it will be poured tomorrow. Removal of curb on the south side of the street will take place later in the week. Impacted residents will be notified.

Meadow Lane: ACTIVE  Weather Delay today
Due to this morning's rain, curb removal of the south side will now take place on Wednesday in  preparation for curb placement on Thursday. Residents will be provided temp access until Thursday morning at 7a.m. 

Wilmot Road (Greenwood to North Ave)    ACTIVE
Phase two of concrete curb and sidewalk repairs will take place later this week. Grinding of the roadway will take place in 1-2 weeks in preparation for resurfacing in 2-3 weeks.

Birchwood Ave: AWAITING SURFACE PAVING 80% complete 
Driveway and parkway restoration is planned over the next 1-2 weeks, Adjustments to underground structures will also take place in preparation for surface course paving in 1-2 weeks.

WarringtonAWAITING SURFACE PAVING 80% complete 
Driveway and parkway restoration is planned over the next 1-2 weeks, Adjustments to underground structures will also take place in preparation for surface course paving in 1-2 weeks.

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 99% complete
Restoration of parkway areas has been completed. Punch list items remain.