Woodland WM Project Update - August 26

Posted on August 26, 2019 at 8:33 AM by Tyler Dickinson

August 26, 2019

Work Completed Last Week:

The boring contractor completed the installation of the new water main along on Oakwood Pl from Woodland Dr to North Ave. With this section of water main installed, the boring contractor has completed their work of installing 4,500 feet of water main.
The underground contractor continued the installation of fire hydrants, water valves, and connections. The underground contractor has completed all underground improvements on Woodland Dr. from Wilmot Rd. to Hawthorne Pl.

Anticipated Schedule for This Week:

The underground contractor will continue with the new water service connections along Woodland Dr. During these connections, short term water disruptions will be required so the homes can be connected to the new main. The contractor will also continue testing the new water main in preparation for the new services to be hooked up. 

Percentage Complete: 59%

Neighborhood Impacts:

Construction operations will necessitate daily lane closures during working hours which may result in delays to
local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.

The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.