Greenwood Weekly Project Update - August 26

Posted on August 26, 2019 at 8:21 AM by Tyler Dickinson

August 26, 2019

Work Completed Last Week:

The contractor adjusted the utility structures within the reconstruction section to final grade. Also, the new detector loops for the Greenwood Ave. / Waukegan Rd. traffic signal were installed.

Anticipated Schedule for This Week:

The contractor will be preparing to begin curb and sidewalk work west of Chestnut St. 

Percentage Complete: 54%

Neighborhood Impacts:

At times, vehicles will not be able to pass the contractor’s work operations which may result in delays to local traffic. Caution should be practiced through the construction work zone and residents must be alert for workers and construction equipment.

The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.