2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Aug 19

Update for Week of 8/19

Posted on August 19, 2019 at 8:28 AM by John Guccione

Meadow Lane: ACTIVE
Curb removal will take place this week in preparation for curb placement.  Physical notifications will be distributed later this week once the schedule is finalized.

WarringtonACTIVE
Base course roadway paving has been completed in time for school opening.  This week the contractor will focus on parkway and driveway restoration.  Adjustments to underground structures will also take place in preparation for surface course paving in 1-3 weeks.

Birchwood Ave:     ACTIVE

Base course roadway paving has been completed in time for school opening.  This week the contractor will focus on parkway and driveway restoration.  Adjustments to underground structures will also take place in preparation for surface course paving in 1-3 weeks.

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 99% complete
Restoration of parkway areas has been completed. Punch list items remain.