Blog module icon

2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Aug 12

Update for Week of 8/12

Posted on August 12, 2019 at 8:34 AM by John Guccione

WarringtonACTIVE
Pavement removal will continue north of Warwick on Warrington Road which will result in daily closures of the roadway to through traffic.  Sub-base preparation will promptly follow pavement removal in this section. Repairs to the concrete sub-base will continue south of Warwick on Warrington Ave.  Paving is planned for Wednesday and Thursday on Warrington Road.   Base course paving will be completed prior to School starting on August 19th.  

Birchwood Ave:     ACTIVE

Pavement removal will begin on Tuesday August 13 and will result in daily closures of the roadway to through traffic.  Sub-base preparation will promptly follow pavement removal. Paving is planned for Friday and Saturday on Birchwood Ave.   Base course paving will be completed prior to School starting on August 19th.  

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 99% complete
Restoration of parkway areas has been completed. Punch list items remain.

Meadow Lane: Awaiting Concrete Crew Availability
Repairs to concrete curbs and sidewalk will take place end of next week or beginning of next. Physical notifications will be hand delivered to residents 48-72 hours previous to impacts.