2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Aug 09

Pavement removal operations continue Saturday August 10 on Warrington Road

Posted on August 9, 2019 at 4:11 PM by John Guccione

WARRINGTON-PAVE_REMOVEPavement removal operations continue Saturday morning at 7:30 a.m. on Warrington Road in preparation for paving next week.

Pavement removal operations on Saturday will include the continuation of 4” grinding moving north on Warrington Road from Westgate Road to Warwick Court and full-depth pavement removal from Warwick Court north to Woodvale Avenue. The full-depth pavement removal will result in the daytime closure of Warrington Road from Warwick Court to Woodvale Avenue. Construction south of Warwick Court will be managed by traffic control flaggers.

Saturday’s work will include patching of the sub surface concrete pavement, which will be plated and passable by motorists once completed.

Once pavement removal is completed early next week, the contractor will shift efforts to sub-base placement north of Warwick Court in preparation for paving Warrington Road, which is planned for the end of next week.