2019 Woodland Watermain Project

Click here to view the complete project details including scope and locations.

View All Posts

Aug 05

Woodland WM Project Update - August 5

Posted on August 5, 2019 at 8:33 AM by Tyler Dickinson

August 5, 2019


Work Completed Last Week:

The boring contractor completed the installation of the new water main along Woodland Dr from Wilmot Rd to Stratford Rd. The boring contractor then began to bore the new water main on Hawthorne Ln.
The underground contractor began the installation of fire hydrants and water main valves.

Anticipated Schedule for This Week:


Today, the underground contractor will install a new connection from the newly installed water main to the existing main on Wilmot Rd.
The boring contractor will also continue to install new water main via direction drilling operations Hawthorne Pl and Woodbine Ct. The underground contractor will continue to install fire hydrants and valves on Woodland Dr from Hawthorne Pl to Stratford Rd. 

Percentage Complete: 31%

Neighborhood Impacts:

Construction operations will necessitate daily lane closures during working hours which may result in delays to
local vehicular traffic. Caution shall be practiced through the construction work zone, and the Village asks that residents be alert for workers and construction equipment.

The Village appreciates your patience while we complete this improvement. If you have any questions or need additional information, please contact the Village of Deerfield Engineering Department at 847-317-2490.

Please be advised that the information communicated here is a forecast of proposed operations which may change due to contractor availability and/or weather conditions.