2019 Street Rehab Project

Click here to view the complete project details including scope and locations.

View All Posts

Aug 05

Update for Week of August 5th

Posted on August 5, 2019 at 7:59 AM by John Guccione

WarringtonACTIVE
Work will begin on Monday August 5th to remove concrete curbs and sidewalk (on the west side of Warrington) in preparation for the concrete curb pour on Tuesday, August 6. Once curbs and sidewalks have been removed on Monday, the contractor will restore access using gravel ramps. These ramps will remain in place until Tuesday morning at 7 a.m.. Sidewalk placement will follow on Thursday. Impacted residents received printed notifications at their properties on Friday, August 2nd.

Birchwood Ave:     ACTIVE

Removal of concrete curb and sidewalks will begin on Tuesday, August 6th on the east side of Birchwood. Concrete curb placement will take place on Wednesday. Sidewalk placement will follow on Friday. Impacted residents will receive printed notifications at their property on Monday, August 5th..

Castlewood, Cranshire, Montgomery, Chatham, Peartree & Village Green: 90% complete
Paving has been completed. Restoration of parkway areas should be completed by the end of this week. Restoration is now 60% complete overall.

Meadow Lane: Awaiting Concrete Crew Availability
Repairs to concrete curbs and sidewalk will take place end of next week. Pavement removal will follow.